Torrance Blvd. Resurfacing
from Torrance Circle to Prospect Ave. and the Torrance Blvd. & Francisca Ave. Traffic Signal Modification Projects 

Construction Notice: 
Hardy & Harper Inc. has been contracted by the City to resurface Torrance Blvd. from Torrance Circle to Prospect Ave. and install new traffic signal at Torrance Blvd. & Francisca Ave. Remaining work includes saw-cutting and removal of asphalt pavement; construction of asphalt pavement; construction of installation of traffic signals, control devices and signs; installation of pedestrian related amenities; installation of a Class II Bike lane; and traffic striping and pavement markings. 

Construction has recommenced this week. Project is anticipated to be completed in March 2024. 

 Construction Schedule, week of: 
02/22/24 – Cold Mill
02/27/24 – ARHM Overlay
03/04/24– Layout striping, Install traffic loops
03/13/24 – Install striping

Traffic Impacts 
There will be temporary closure of traffic lanes and redirection of the pedestrian path to facilitate the work.  Through traffic will be accommodated at all times subject to intermittent delays. 

Work Hours 
7:00 am to 6:00 pm (Monday - Friday) with lane closures only permitted between 9:00 am to 3:00 pm 

Contact Information 

Hardy & Harper, Inc. Contacts: 
Superintendent John Godinho, Cell: 760-275-0642 or Office: 714-444-1851 ext. 135 
Project Manager Megan Kathriner, Cell: 714-393-0113 or Office:714-444-1851 ext.123 
On-site Construction Foreman Frank Perez, Cell: 949-315-8696 

City of Redondo Beach Contacts: 
Construction Manager Davina Buenavista, 310-766-6985 
Project Inspector Anthony English, 310-869-8598
Project Manager Daniel Gruezo, 310-697-3214 

 