Phase 8-A Residential Resurfacing Project Begins

As part of the Phase 8-A Residential Street Resurfacing Project, three streets within the Harbor area are set for resurfacing beginning the week of June 7th.  

The construction process includes one day for grinding / removing the existing pavement with repaving occurring the next day. 

 
Construction Schedule:
                                                               Grinding           
Paving
George Freeth Way and Yacht Club Way:    06/07/10        06/08/10
Marina Way and Portofino Way                  06/14/10         06/15/10
 
In the event of questions / comments concerns, the contractor and the City have provided contact information:
 
Contractor information:
All American Asphalt
Doug Harrington, Construction Manager: 
Office: 951-736-7600
Cell: 951-453-9000
Mike Flom, Public Works Superintendent: 
Office: 951-736-7600 
Cell: 951-453-7498

City information:

Karl Karunatilaka, City Public Works Inspector:
Cell: 323-819-8926
 